August 7, 2025
Two roundabouts on Coleman’s Crossing Boulevard, one at East Fifth Street and one at the western entrance of Walmart, as shown above, will be the first phase of intersection upgrades done on the roadway sometime in the next 1-2 years. Work will also include adding a median, eliminating many of the left turn options for those parking lots. (Graphic submitted)

Roundabout nears completion

 

By Michael Williamson, Richwood Gazette

The roundabout project at Coleman’s Crossing Boulevard and Industrial Parkway is progressing ahead of schedule and is likely 2-3 weeks from opening.

Kyle Hoyng, engineer at the City of Marysville, said the project was given given three months to be completed, putting the opening sometime in mid-September, but the work could be finished later this month.

“They started the second week of June, so we’re about six weeks in,” he said. “So, that is going to wrap up probably just under three months.”

He said some of that is due to the fact that crews had decent weather but mostly to do with the intersection being closed completely d…

Read this entire article as it appeared in print in our eEdition

LATEST NEWS
Village PSA
Local News
The Richwood Village Council would like to remind residents that tree-limb pickup, beginning on April 1, 2026, is only for fallen tree branches. Trash...
March 26, 2026
Richwood Community Meals
Community
Thursday, March 26 Roast Pork/Gravy, Hash Brown Casserole, Buttered Lima Beans, Warm Scalloped Apples, 2 Orange Cranberry Scones Friday, March 27 Cabb...
March 26, 2026
Community
From Gazette staff reports The Rhinehart United Methodist Women will be sponsoring their 25th annual spring craft/vendor/home show on Saturday, April ...
March 26, 2026
Community
Check out our list of events and activities. Key Events and Activities 1. Trips: Our Canada trip is full, but we are making a waiting list. If this is...
March 26, 2026