Logjam
December 5, 2024

Logjam work to begin in December

 

By Michael Williamson, Richwood Gazette

Residents along Mill Creek should notice crews moving in to clear logjams starting the second week of December.

The Union County Commissioners approved the contract with H and H Land Clearing at the Wednesday regular board meeting. Now that it has been approved, the company can be released for construction.

H and H beat out four other companies that sent in bid packets, winning with the lowest bid of $2,676,715 for a project that was estimated to cost nearly $4 million.

County Engineer Jeff Stauch said officials have met with the contractor several times including a pre-construction meeting last week. He said the work is set to start the…

Read this entire article as it appeared in print in our eEdition

LATEST NEWS
Community
100 YEARS AGO From Oct. 28, 1926 Certain interests in Idaho are striving to get through Congress an act which would cut 8000 acres out of Yellowstone ...
October 30, 2026
Community
FIRE Oct. 20 10:28 a.m. – Route 47 (car fire) 11:45 a.m. – North Franklin Street (trash fire) 6:41 p.m. – Route 47 (trash fire) Oct. 22 2:39 p.m. – Bl...
October 30, 2026