Cadence Solar project to begin construction

 

By Michael Williamson, Richwood Gazette

Construction on the Cadence Solar project is set to start soon according to an updated timeline from Invenergy, the company behind it.

Erin Saal, renewable development manager with Invenergy, told the Union County Commissioners last week that while there were slow-downs in the beginning, the project is now on track to begin its construction phase next month.

Cadence will be located in York, Liberty, and Taylor townships between Routes 47 and 347, bisected in the center by Route 739.

Some early work was done last year including tree clearing and the installation of some access roads, but Saal said the company paused in December until furt…

Read this entire article as it appeared in print in our eEdition

LATEST NEWS
Hajjar honored by CBC for October
Local Sports
By BOB PUTMAN Nickolas Hajjar of North Union was among those named as an athlete of the month in the Central Buckeye Conference for the month of Octob...
November 5, 2026
Richwood Community Meals
Community
Nov. 6 Chicken & Noodles, Steamed Broccoli, Tomato & Onion Salad, Peaches, 2 oz. Cornbread Muffin Nov. 9 Cheese Tortellini/Marinara, Buttered ...
November 5, 2026
Community
Our big trip for the spring of 2027 is Shipshewana, Indiana, on Tuesday, May 18 through Thursday, May 20. An adventure in Amish Country with guided to...
November 5, 2026
Fire – EMS
Community
FIRE Oct. 26 7:07 p.m. – North Franklin Street (MVA) Oct. 28 5:15 p.m. – Darby Pottersburg Road (house fire) Oct. 30 10:46 a.m. – Herbert Street (wire...
November 5, 2026
Police Beat
Community
From Richwood Division of Police reports: Oct. 25 An officer responded to North Fulton Street at 2:23 a.m. for a well-being check. A trespassing compl...
November 5, 2026