Cadence
May 2, 2024

Cadence Solar project to begin construction

 

By Michael Williamson, Richwood Gazette

Construction on the Cadence Solar project is set to start soon according to an updated timeline from Invenergy, the company behind it.

Erin Saal, renewable development manager with Invenergy, told the Union County Commissioners last week that while there were slow-downs in the beginning, the project is now on track to begin its construction phase next month.

Cadence will be located in York, Liberty, and Taylor townships between Routes 47 and 347, bisected in the center by Route 739.

Some early work was done last year including tree clearing and the installation of some access roads, but Saal said the company paused in December until furt…

Read this entire article as it appeared in print in our eEdition

LATEST NEWS
Community
Easy ways to support our activities and events are by buying a drink from Richwood Coffee. We receive 100% of the proceeds. Key Events and Activities ...
October 22, 2026
Richwood Community Meals
Community
Friday, Oct. 23 BBQ Ribs, Butternut Squash, Corn Casserole, Watergate Salad, Dinner Roll, Cake Monday, Oct. 26 Spaghetti w/meat sauce, Steamed Zucchin...
October 22, 2026
Fire – EMS
Community
FIRE Oct. 12 5:17 p.m. – Welsh Place (cancelled) Oct. 14 3:39 p.m. – Route 4 (grass fire) Oct. 16 4:51 p.m. – Miller Road (MVA) Oct. 17 4:21 p.m. – Sc...
October 22, 2026
U.C. Airport receives $720K state grant
Local News
The Union County Airport recently received over $700,000 in state funding to rehab its terminal area. At the regular meeting of the airport authority ...
October 22, 2026
NU has options for  SRO funding
Local News
The North Union Board of Education discussed three options for school resource officer (SRO) funding that were provided by the Union County Sheriff’s ...
October 22, 2026