Acciona solar project should be completed by spring

 

By Michael Williamson, Richwood Gazette

Construction of the Acciona solar project is nearing completion and officials said it should be finished by spring.

Union County Administrator Bill Narducci updated the commissioners last week on the company’s Union Solar project, which began construction more than a year ago.

Narducci said he recently met with Brian Dunnebeck, development manager with Acciona, who said the project is over 90% complete as of the start of the year.

“The update that he provided shows they’re, overall, about 92% complete with construction of the project and the majority of that, 80%, is testing and commissioning,” he said. “According to him, modul…

Read this entire article as it appeared in print in our eEdition

LATEST NEWS
Union County EMA issues heat wave warning
Local News
From Gazette staff reports The Union County Emergency Management Agency (EMA) issued an extreme heat watch warning in the area from Sunday to Wednesda...
June 26, 2025
RABA  hosts AED training
Community
From Gazette staff reports The Richwood Area Business Association (RABA) will be hosting an Automated External Defibrillator (AED) training session in...
June 26, 2025
Fire – EMS
Community
FIRE June 16 11:05 p.m. – Snediker Road (electrical short) June 18 7:21 p.m. – West Mansfield / Mount Victory Road (lines down) 8 p.m. – Route 37 (lin...
June 26, 2025
Soft serve for softball squad
Local News
A club softball team makes a dash for cold treats at Chefs’ Parlour Monday evening after playing in the sweltering heat. Temperatures in the village a...
June 26, 2025