Acciona
January 18, 2024

Acciona solar project should be completed by spring

 

By Michael Williamson, Richwood Gazette

Construction of the Acciona solar project is nearing completion and officials said it should be finished by spring.

Union County Administrator Bill Narducci updated the commissioners last week on the company’s Union Solar project, which began construction more than a year ago.

Narducci said he recently met with Brian Dunnebeck, development manager with Acciona, who said the project is over 90% complete as of the start of the year.

“The update that he provided shows they’re, overall, about 92% complete with construction of the project and the majority of that, 80%, is testing and commissioning,” he said. “According to him, modul…

Read this entire article as it appeared in print in our eEdition

LATEST NEWS
Fire – EMS
Community
FIRE Feb. 22 9:05 p.m. – Beatty Avenue (CO check) Feb. 23 1:58 p.m. – Route 4 (MVA) Feb. 28 11:39 p.m. – Route 739 (MVA) EMS Feb. 24 2:28 p.m. – East ...
March 5, 2026
A mission to Belize
Local News
Members of the outreach team with Fulton Creek Friends Church are currently serving villagers in southern Belize as part of a humanitarian mission to ...
March 5, 2026
Former Wings director charged
Local News
A former director at a local non-profit has been indicted after allegedly receiving over $250,000 in salary over the course of three years while emplo...
March 5, 2026
Madison  County solar makes payment
Local News
By Michael Williamson, Richwood Gazette While officials in Union County are still wondering exactly how solar farm revenue will play out, those in Mad...
March 5, 2026